Leeds Airport Commercial Construction Project

Building a Specialised Acoustic Testing Room

Overview:

D Blackburn Contractors successfully constructed a specialized acoustic testing room for Leeds Airport, meeting strict specifications for sound isolation and safety within a demanding commercial environment.

Problem:

Leeds Airport needed a dedicated acoustic room for testing the sounds of airplane engines, with specific requirements for:

  • Acoustic Performance: The room had to meet stringent acoustic standards for sound isolation.

  • Specific Construction: The design required steelwork, blockwork infill, and a specialized white rock cladding.

  • Strict Safety Protocols: The airport environment demanded strict adherence to health and safety regulations.

Solution:

We provided a specialized construction solution:

  • Specialised Construction: Built the acoustic room according to the airport's specifications, using steelwork, blockwork infill, and white rock cladding.

  • Formwork Concrete: Constructed formwork (timber boxes) to create a continuous concrete ring beam on top of the blockwork, using a boom pump to precisely pour the concrete.

  • Electrical Installation: Installed electricity for lighting and sockets within the acoustic testing room.

  • Adherence to Safety Standards: Strictly adhered to all health and safety protocols, including risk assessments, method statements, and COSHH regulations.

Results:

  • Successful Project Completion: The acoustic testing room was completed within the six-week timeframe.

  • Acoustic Performance Met: The room met the airport's stringent acoustic requirements for testing airplane engines.

  • Client Satisfaction: The airport authorities were extremely happy with the quality of the construction and the adherence to safety regulations.